Research on Schedule Control of Large Scale Complex Project Based on BIM and PDCA Theory(PDF)

《建筑科学与工程学报》[ISSN:1673-2049/CN:61-1442/TU]

Issue:
2022年04期
Page:
183-191
Research Field:
Publishing date:

Info

Title:
Research on Schedule Control of Large Scale Complex Project Based on BIM and PDCA Theory
Author(s):
ZHANG Yu-zhuo1 ZHANG He1 WANG Qing-he2 ZHANG Xin-long3
(1. School of Management, Shenyang Jianzhu University, Shenyang 110168, Liaoning, China; 2. School of Civil Engineering, Shenyang Jianzhu University, Shenyang 110168, Liaoning, China; 3. China Northeast Architectural Design & Research Institute Co., Ltd, Shenyang 110003, Liaoning, China)
Keywords:
large scale complex project BIM technology PDCA theory schedule control
PACS:
TU937.2
DOI:
10.19815/j.jace.2021.08035
Abstract:
Taking the large scale complex project as the research object, the fine simulation of construction progress was carried out based on the building information model(BIM). On this basis, a construction progress management method was proposed to effectively improve the engineering informatization level. Firstly, the three-dimensional BIM model was established by parametric modeling method, and was imported into Glodon BIM5D platform to generate a four-dimensional model. The plan-implementation-check-disposal(PDCA)theory was combined with BIM technology, and it was applied to the combination point one(the whole process of construction progress control from a macro perspective)and the combination point two(the BIM strengthening application of key links in construction progress control). Finally, the method was applied to a large complex project schedule control example to verify its feasibility. The results show that the combination of BIM technology and PDCA cycle management theory can make the schedule control objectives clearer and the schedule management process more optimized in whole construction process. The number of schedule simulation in the second area of the actual construction section is reduced by 60%, and the overall construction period is 3.5% ahead of schedule. Therefore, the combination of BIM and PDCA can effectively improve the level of engineering informatization, and provide new ideas for the establishment of scientific and effective schedule management methods.

References:

[1] 鲍跃全,李 惠.人工智能时代的土木工程[J].土木工程学报,2019,52(5):1-11.
BAO Yue-quan,LI Hui.Artificial Intelligence for Civil Engineering[J].China Civil Engineering Journal,2019,52(5):1-11.
[2]刘占省,刘诗楠,赵玉红,等.智能建造技术发展现状与未来趋势[J].建筑技术,2019,50(7):772-779.
LIU Zhan-sheng,LIU Shi-nan,ZHAO Yu-hong,et al.Development Status and Future Trends of Intelligent Construction Technology[J].Architecture Technology,2019,50(7):772-779.
[3]刘吉臣,高 莹,侯寰宇.基于建筑信息建模技术的城市综合体设计实践研究[J].工业建筑,2019,49(2):184-188.
LIU Ji-chen,GAO Ying,HOU Huan-yu.Research on Practice for Urban Complex Design Based on BIM Technology[J].Industrial Construction,2019,49(2):184-188.
[4]钟 炜,张凯乐,乜凤亚.海南酒店项目BIM-5D精细化管理研究[J].土木建筑工程信息技术,2017,9(2):24-29.
ZHONG Wei,ZHANG Kai-le,NIE Feng-ya.Research on BIM-5D Fine Management in Hainan Hotel Project[J].Journal of Information Technology in Civil Engineering and Architecture,2017,9(2):24-29.
[5]曾 波,朱 洁,杨文博,等.BIM技术在大型城市综合体工程智能建造中的应用[J].建筑施工,2017,39(6):903-905.
ZENG Bo,ZHU Jie,YANG Wen-bo,et al.BIM Technology Applied to Intelligent Construction of Large Urban Complex Engineering[J].Building Construction,2017,39(6):903-905.
[6]樊 军,王 璟.BIM技术在项目进度管控中的应用[J].土木建筑工程信息技术,2019,11(6):66-69.
FAN Jun,WANG Jing.Application of BIM Technology in Schedule Management of Project[J].Journal of Information Technology in Civil Engineering and Architecture,2019,11(6):66-69.
[7]王 婷,任琼琼,肖莉萍.基于BIM5D的施工资源动态管理研究[J].土木建筑工程信息技术,2016,8(3):57-61.
WANG Ting,REN Qiong-qiong,XIAO Li-ping.Dynamic Management Research on Construction Resources Based on BIM5D[J].Journal of Information Technology in Civil Engineering and Architecture,2016,8(3):57-61.
[8]琚 娟.BIM技术在超大型商业综合体项目中的应用[J].土木建筑工程信息技术,2019,11(2):75-78.
JU Juan.Application of BIM Technology in Super Large Commercial Complex Project[J].Journal of Information Technology in Civil Engineering and Architecture,2019,11(2):75-78.
[9]秦 康.基于BIM和PDCA的施工进度管理研究[D].南宁:广西大学,2016.
QIN Kang.The Construction Schedule Management Based on BIM and PDCA[D].Nanning:Guangxi University,2016.
[10]单 佳.BIM技术在大型商业综合体建设项目管理中的运用[J].建筑施工,2019,41(7):1381-1383.
SHAN Jia.Application of BIM Technology in Project Management of Large-scale Commercial Complex Construction[J].Building Construction,2019,41(7):1381-1383.
[11]乔 堃,张 亮.建筑信息模型在上海国际旅游度假区某主题公园施工全周期中的应用[J].工业建筑,2016,46(5):192-197.
QIAO Kun,ZHANG Liang.Application of BIM to Whole Construction Cycle of a Theme Park in Shanghai International Tourism Resort[J].Industrial Construction,2016,46(5):192-197.
[12]刘德富,彭兴鹏,刘绍军,等.BIM5D在工程项目管理中的应用[J].施工技术,2017,46(增2):720-723.
LIU De-fu,PENG Xing-peng,LIU Shao-jun,et al.The Application of BIM5D in Project Management[J].Construction Technology,2017,46(S2):720-723.
[13]林佳瑞,张建平,钟耀锋.基于4D-BIM的施工进度-资源均衡模型自动构建与应用[J].土木建筑工程信息技术,2014,6(6):44-49.
LIN Jia-rui,ZHANG Jian-ping,ZHONG Yao-feng.Schedule-resource Trade-off Modeling and Application Based on 4D-BIM[J].Journal of Information Technology in Civil Engineering and Architecture,2014,6(6):44-49.
[14]王 珺,张人友.BIM3维与4维建模实例[J].工业建筑,2012,42(7):179-182,141.
WANG Jun,ZHANG Ren-you.Case History of BIM 3D and 4D Modelings[J].Industrial Construction,2012,42(7):179-182,141.
[15]陈礼松,汪夏明,秦 康,等.基于BIM和PDCA的施工进度管理研究[J].施工技术,2019,48(7):131-137.
CHEN Li-song,WANG Xia-ming,QIN Kang,et al.Research on Construction Schedule Management Based on BIM and PDCA[J].Construction Technology,2019,48(7):131-137.
[16]马 波.PDCA管理法在预埋件现场设计复查中的应用[J].工业建筑,2014,44(增):1109-1111,1108.
MA Bo.Application of PDCA Methods in Site Design Reviewing of Embedded Parts[J].Industrial Construction,2014,44(S):1109-1111,1108.
[17]唐江舟,李 静,邓 芳.PDCA循环模型在工程造价管理中的应用研究[J].经济师,2021(4):293,295.
TANG Jiang-zhou,LI Jing,DENG Fang. Application of PDCA Cycle Model in Project Cost Management[J].China Economist,2021(4):293,295.
[18]张树懿,刘莹莹,刘永昌.基于BIM+PDCA循环控制的EPC总承包模式设计质量研究[J].项目管理技术,2018,16(12):121-124.
ZHANG Shu-yi,LIU Ying-ying,LIU Yong-chang.Research on Design Quality of EPC General Contracting Mode Based on BIM+PDCA Cycle Control[J].Project Management Technology,2018,16(12):121-124.

Memo

Memo:
-
Last Update: 2022-07-10